Progress report - November 2019

Work is progressing well, despite recent very poor weather.

We are currently at 60 percent completion, which looks good for our planned finish date of Mid-January 2020.

So far 60,000 tonnes of surfacing has been renewed, much of it using the cold-recycling process which reuses old materials, reducing waste and the number of truck movements needed.

We have replaced line markings on 29,000 metres of carriageway and 1700 road studs.

Traffic recently was changed onto the other side of the carriageway. This change went really well and we are grateful for customers' cooperation and patience.

There is now a temporary 60mph speed limit in place through the work area which we hope will improve journey reliability.

Posted on 5th November 2019

by Kate Read